Front access – bottom incoming cables, Figure 11 – Rockwell Automation 1512A MV Controllers, 400A One-High Cabinet, Standard and Arc-Resistant Enclosure User Manual

Page 18

Advertising
background image

10

Rockwell Automation Publication 1512A-UM100F-EN-P - May 2013

Chapter 2

Installation – Standard Enclosure

10. Reverse procedure after cables have been installed.

Figure 11 - Power Bus with Barrier Removed

Front Access – Bottom Incoming Cables

If the incoming cables in your cabinet enter the section from the bottom, follow
the same procedure as for

Front Access – Top Incoming Line Cables

.

1. Open the power cell door.

2. Locate incoming cable duct at rear left-hand side of power cell (see

Figure 12

).

3. Remove self-tapping screws from the cable duct access barriers. Remove

barriers.

4. Route and install incoming line cables to power bus. Torque to

specifications (refer to

Recommended Torque Values on page 2 of

Chapter 1

).

5. Reverse procedure after cables have been installed.

ATTENTION: Ensure all barriers are replaced before re-energizing the
equipment. Failure to do so may result in electrical faults and cause damage to
equipment or severe injury to personnel.

TIP

Access to incoming cable duct in the power cell is also required.

Low Voltage Panel

Power Bus

Advertising