Appendix B

ArcShield Plenum Installation Instructions

Cabinet Preparation

In preparation for mounting Plenum, remove 1/4-20 fasteners from the Relief
vent on the top of the MV enclosure. .

The Plenums are designed to fit over the fastener heads at the four corners of the
Relief vent. The corner fasteners are required to secure the Relief vent during
installation.

Plenum Placement on Structure

Once the Plenum has been lifted in place directly over the relief vent (shown in

Figure 75

), all 1/4-20 fasteners, removed in

Cabinet Preparation

above, are

replaced to attach the Plenum to the top of the enclosure. Use hand tools only.

IMPORTANT

Do not remove the four corner fasteners (

Figure 74

)

Figure 73 - Typical Relief Vent Fasteners (top view)

Figure 74 - Relief Vent

Relief vent

Relief fasteners

Corner fasteners