Figure 13 – Rockwell Automation 1512A MV Controllers, 400A One-High Cabinet, Standard and Arc-Resistant Enclosure User Manual

Page 20

Advertising
background image

12

Rockwell Automation Publication 1512A-UM100F-EN-P - May 2013

Chapter 2

Installation – Standard Enclosure

3. Load cables for the power cell should be routed before control cables. Pull

the cables into the cabinet through the appropriate opening (see

Figure 13

to

Figure 15

).

4. Remove current transformer barriers.

5. Connect the cables to the current transformers and tighten the

connections to 65 N•m (48 lb•ft).

6. Connect cable shields (if present) to the ground lug.

7. Reinstall the current transformer barrier and reassemble the cabinet.

Figure 13 - Access to Load Cable Conduit Openings (Bottom Entry)

Figure 14 - Load Cable Conduit Openings, Bottom Exit