7.

The Analyzer PRO instrument is now

securely mounted to the fabricated
frame. It is ready to be mounted to the
final process location.

Verify that all hardware is secure.
Protect the fiber (if so equipped) as
well as the power and
communications cables.

Carefully move the Analyzer PRO
instrument and mounting frame to the
final location.

8.

Mounting studs should be placed in

the correct positions to hold the frame
in place.

We installed 3/8” studs in the
mounting area as shown. These are
21.75” (552mm ) apart, which
corresponds with the slot holes in our
mounting frame. The lower studs are
mounted 22” (560mm) below, at the
same width.

These studs should be capable of
supporting the weight of the Analyzer
PRO instrument and frame, with a
large margin of safety. Be sure to
measure for the frame used, and

9.

Roll the cart so the mounting frame is

directly in front of the mounting studs.

Using the lab jacks, raise the Analyzer
PRO instrument (on the mounting
frame as shown) to the correct
position. When the studs align with
the mounting frame, gently ease the
mounting frame over the studs as
shown.