EFCO CORPORATION 6/2012

PART NO. Y554

Series 5500 Silicone Structural Glazed Curtain Wall Installation Instructions

STEP #3 INSTALL FRAME COMPONENTS

A. Repeating step 2, page 18, set each successive frame into the opening, snapping the verti-

cals and fillers at each frame, until all frames are installed up to the last frame at the op-

posite jamb.

B. Check frequently to ensure the installed framing is in the proper position with regard to

established benchmarks.

C. After securing the anchor bolts, snap-in head and sill fillers.

Section III: Typical Anchorage Methods

* NOTE: On long runs, check overall frame dimensions at every fifth opening to avoid

dimensional build-up. The commercial cut length tolerance is +/- 1/16”. It is critical

to check every fifth unit for location relative to established benchmarks.

See Step 4, page

20 for special

sealant note for
intermediate

horizontals.

See Step 1,

page 26 for

special sealant
note for SSG

head and sills

used with SSG

verticals.

See Step 1,

page 26 for

special sealant
note for SSG

head and sills

used with SSG

verticals.

See Step 2, page 27

for special sealant

note for captured
horizontals used

with SSG verticals.

BUILDING ROUGH

OPENING

ASSEMBLED

FRAME