EFCO S5500 SSG User Manual

Page 50

Advertising
background image

EFCO CORPORATION 6/2012

PART NO. Y554

Series 5500 Silicone Structural Glazed Curtain Wall Installation Instructions

Section VII: Door Framing Installation & Anchorage

STEP #8 INSTALL DOOR HEAD SUBFRAME

Unless a concealed overhead closer is used, a subframe will be required at the door head. See the de-
tail below for the optional door header for concealed overhead closer applications.

A. The subframe at the door head is cut to run between the vertical subframes. Apply sealant

to each end of the subframe. Set the subframe into the opening at the door head, making

sure the leg of the subframe is in the glazing pocket. Pull the subframe toward the face of

the door head, making sure it is flush with the exterior.

B. Match drill the door head, and fasten the subframe as shown in the detail below with a

fastener spacing maximum of 12” on center. Refer to the approved shop drawings for fas-

tener types.

C. Tool the sealant at each end of the subframe, and remove any excess sealant that remains.

STANDARD DOOR HEAD DETAIL

OPTIONAL

COC HEADER

SUBFRAME

SEALANT

Note: An inside glazed

horizontal must be used

at the next horizontal
immediately above a

concealed overhead

closer horizontal. The

glazing cannot be outside

set in this detail.

DOOR HEAD W/ CONCEALED OVERHEAD CLOSER DETAIL