EFCO S5500 SSG User Manual

Page 22

Advertising
background image

EFCO CORPORATION 6/2012

PART NO. Y554

Series 5500 Silicone Structural Glazed Curtain Wall Installation Instructions

IMPORTANT NOTE:

It is critical to allow at least a 3/4” space between the perimeter of the jamb mullion

and the condition for setting space for the last frame unit to be installed.

Section III: Typical Anchorage Methods

STEP #5 INSTALL FRAME COMPONENTS

A. Set the last frame in the run into the opening mating the filler with the intermediate

vertical until the filler and vertical snap together.

B. When the frame is set level and plumb, apply the dead load shims below the verticals,

and apply anchors as shown in Step 2 (B), pages 18 and 19.

C Snap-in the sill fillers.

D. Refer to Sections IV and V for Glazing Preparation and Glazing Installation.

Apply dead load

shims at anchors

and below verticals.

SILL

FILLERS

See Step 4, page 20, Step 2,

page 27, and Step 3, page 28

for special sealant note for
captured horizontals used

with SSG verticals.