Series 5500 Silicone Structural Glazed Curtain Wall Installation Instructions

Section VII: Door Framing Installation & Anchorage

STEP #9 INSTALL DOOR STOPS

A. First, install the door stop at the head. This stop is cut the same length as the door head

subframe.

B. The vertical door stops are cut to run from the condition at the sill, to the bottom of the

door head subframe. The tops of the stops are notched as shown in the drawing inset. In-

sert the flat part of the stop that remains at the top of the door stop under the door stop at

the head as shown.

C. Snap the stop into the pocket of the subframe.

D. Install any required hardware and hang the doors per the approved shop drawings.

SUBFRAME

SUBFRAME

5/8” notch flush

as shown.

DOOR STOP

DOOR STOP

DOOR JAMB

DOOR HEADER