EFCO CORPORATION 6/2012

PART NO. Y554

Series 5500 Silicone Structural Glazed Curtain Wall Installation Instructions

Section IV: Glazing Preparation

STEP #1 PREPARE FRAME FOR JOINT PLUGS

In some instances, projects will require captured and SSG mullions used in combination

within the same elevation. Use the following steps as a guide in these situations.

A. Fill the gasket and adapter raceways with sealant to close off the void at the joint

plug locations. The sealant height should be a minimum of 1” long.

B. Seal all connecting surfaces of the horizontal and vertical mullions with sealant

for the application of the mullion joint plugs. Tool sealant into the joints at the

thermal strut.

Fill gasket and adapter

raceways with sealant.

Apply sealant to mullion

surfaces that will contact

joint plugs.

OPTIONAL CAPTURED VERTICAL AND

CAPTURED HORIZONTALS

Seal the ends of the front

part of the horizontals to

the vertical mullion.

Seal the ends of the front

part of the horizontals to

the vertical mullion.