EFCO S5500 SSG User Manual

Page 49

Advertising
background image

EFCO CORPORATION 6/2012

PART NO. Y554

Series 5500 Silicone Structural Glazed Curtain Wall Installation Instructions

Section VII: Door Framing Installation & Anchorage

STEP #7 INSTALL VERTICAL SUBFRAMES

A. Apply sealant into the glazing gasket reglets of the exterior covers of the door jambs and

door header as shown.

B. The vertical subframes are cut to run from the condition at the sill through to the bottom

of the door header with the head subframe running in between. Apply sealant to each end

of the subframe. Set the vertical subframes into the opening on the sides of the door

jambs, making sure the legs of the subframes are in the glazing pocket. Pull the sub-

frames toward the face of the door jamb, making sure it is flush with the exterior.

C. Match drill the door jamb and fasten the subframe as shown in the detail below with a fas-

tener spacing maximum of 12” on center. Refer to the approved shop drawings for fas-
tener types.

D. Tool the sealant at each end of the subframe, and remove any excess sealant that re-

mains.

ANCHOR CLIP

ANCHOR CLIP

ATTACHMENT

SCREWS

ANCHOR BOLTS

AS REQUIRED

SUBFRAME

DOOR JAMB

SUBFRAME

ATTACHMENT

SCREWS

SEALANT

Advertising