Bradford White BLMC125NA User Manual

Page 32

Advertising
background image

Page 30

Bradford White Corp.

system is ready for operation.

12. Refer to local codes and the make-up water valve

manufacturer’s instructions as to whether the

make-up water valve should be left open or closed.

13. After placing the unit in operation, the ignition

system safety shutoff device must be tested.

First, shut off the manual gas valve, and call the

unit for heat. Main gas terminals will be energized,

attempting to light, for four (4) seconds, and then

will de-energize. The unit will go into lockout after

the required number of trial for ignition periods.

Second, turn the power off, press the manual reset

button on the boiler control, or the user display,

open the manual gas valve and allow the unit to

light. While the unit is operating, close the manual

gas valve and ensure that power to the main gas

valve has been cut.

14. Within three (3) days of start-up, recheck all air

bleeders and the expansion tank as described in

Steps 4 and 8 above.

Important Note: The installer is responsible for

identifying to the owner/operator the location of all

emergency shutoff devices.

WARNING

Do not use this appliance if any part has been under

water. Immediately call a qualified service technician

to inspect the appliance

and to replace any part of the control system and any

gas control that may have been

under water.

10.2 Starting the Burner after Set Up

Initial setup must be checked before the unit

is put in operation. Problems such as failure to start,

rough ignition, strong exhaust odors, etc. can be due

to improper setup. Damage to the boiler resulting from

improper setup is not covered by the limited warranty.

10.2.1 Burner Operation

REQUIRED TOOLS:

differential pressure

gauge capable of reading negative 0.01 inches W.C.

(0.002kPa), screw drivers, and combustion analyzer.
1. Using this manual, make sure the installation

is complete and in full compliance with the

instructions and all local codes.

2. Determine that the appliance and system are filled

with water and all air has been bled from both.

Open all valves.

3.

Observe all warnings on the Operating

Instructions (Start Up / Shut Down

Instruction ) Decal, located on the back

of the Top Front Cover, and turn on gas

and electrical power to appliance.

SECTION 10.

Set Up Instructions

10.1 Filling the Boiler System

1. Ensure the system is fully connected. Close all

bleeding devices and open make-up water valve.

Allow system to fill slowly.

2. Move manual lever on 3-way valve actuator to

"open" position, allowing air to purge from boiler

loop. Valve is normally in DHW position until

there is a call for Central Heat via "T-T" contacts.

If make-up water pump is employed, adjust

pressure switch on pumping system to provide a

minimum of 12 psi (81.8 kPa) at the highest point

in the heating loop.

3. If a water pressure regulator is provided on the

make-up water line, adjust the pressure regulator

to provide at least 12 psi (81.8 kPa) at the highest

point in the heating loop.

4. Open bleeding devices on all radiation units at the

high points in the piping throughout the system,

unless automatic air bleeders are provided at such

points.

Note that there is an air bleed located on the left

side of Brute Elite, on top of the jacket.

5. Cycle the boiler pump on and off 10 times, 10

seconds on and 10 seconds off to remove all air

from the heat exchanger. Then run system and

appliance pump for a minimum of 30 minutes with

the gas shut off.

6. Using manual lever located on left side of 3-way

valve actuator, move from "open" position back to

closed position repeatedly. This process forces air

out of the internal DHW loop.

WARNING

Failure to remove all air from the heat exchanger could

lead to property damage, severe injury or death.

7. Recheck all air bleeders as described in Step 4.
8. Start up boiler according to the procedure in this

manual. Operate the entire system, including the

pump, boiler, and radiation units for one (1) hour.

9. Shut down the entire system and vent all radiation

units and high points in the system piping, as

described in Step 4.

10. Close make-up water valve and check strainer in

pressure reducing valve for sediment or debris

from the make-up water line. Reopen make-up

water valve.

11. Check gauge for correct water pressure and also

check water level in the system. If the height

indicated above the boiler insures that water is at

the highest point in the circulating loop, then the

Advertising