1 gas supply and piping – LAARS Mascot LX MLXC 175 MBH - Install and Operating Manual User Manual

Page 21

Advertising
background image

Mascot LX Boilers and Water Heaters

Page 17

WARNING:

Open flame can cause gas to ignite and result in

property damage, severe injury, or loss of life.

NOTE: The Mascot LX appliance and all other gas

appliances sharing the gas supply line must be firing at

maximum capacity to properly measure the inlet supply

pressure. The pressure can be measured at the supply

pressure port on the gas valve. Low gas pressure could

be an indication of an undersized gas meter, undersized

gas supply lines and/or an obstructed gas supply line.

SCHED 40 METAL PIPE CAPACITY FOR 1.50 SPECIFIC GRAVITY

UNDILUTED PROPANE

NOMINAL PIPE SIZE

@

11" W.C. INLET AND 0.5" W.C. PRESSURE DROP

SIZE

1/2" 3/4" 1"

LENGTH MAXIMUM CAPACITY IN THOUSANDS OF BTU PER
HOUR

20

200 418 787

40

137 287 541

60

110 231 434

80

94

197 372

100

84

175

330

NOTES: 1. Follow all local and national LP gas codes for line sizing and

equipment requirements. 2. Verify that inlet gas pressure remains between

4 and 13 inches of water column before and during operation.

Source: ANSI Z223.1-80 National Fuel Gas Code.

Table 9. Nominal Pipe Size, Propane

SCH 40 METAL PIPE CAPACITY FOR 0.60 SPECIFIC GRAVITY NATURAL GAS

NOMINAL PIPE SIZE

@

0.30" W.C. PRESSURE DROP

LENGTH

1/2" 3/4" 1"

FT CUBIC FEET OF GAS PER HOUR

20

92 190 350

40

130 245

60

105 195

80

90 170

100

Table 10. Nominal Pipe Size, Natural Gas

SECTION 4.

Gas Supply and Piping

4.1 Gas Supply and Piping

Gas piping should be supported by suitable hangers or

floor stands, not the appliance.
Review the following instructions before proceeding

with the installation.
1. Verify that the appliance is fitted for the proper type

of gas by checking the rating plate. Mascot LX will

function properly without the use of high altitude

modification at elevations up to 10,000 feet (3050

m).

2. The maximum inlet gas pressure must not exceed

13" W.C. (3.2kPa). The minimum inlet gas pressure

is 4" W.C. (1.0kPa).

3. Refer to

Table 11, Table 10, Table 9 and Table 12

to

size piping.

4. Run gas supply line in accordance with all

applicable codes.

5. Locate and install manual shutoff valves in

accordance with state and local requirements.

6. A sediment trap must be provided upstream of the

gas controls.

7. All threaded joints should be coated with piping

compound resistant to action of liquefied petroleum

gas.

8. The appliance and its individual shutoff valve must

be disconnected from the gas supply piping during

any pressure testing of that system at test pressures

in excess of 1/2 PSIG (3.45kPa).

9. The unit must be isolated from the gas supply

system by closing its individual manual shutoff

valve during any pressure testing of the gas supply

piping system at test pressures equal to or less than

1/2 PSIG (3.45kPa).

10. The appliance and its gas connection must be leak

tested before placing it in operation.

11. Purge all air from gas lines.

Advertising