CIRCUTOR CDP-0 User Manual

Page 29

Advertising
background image

CDP

Instruction Manual

29

Table 12: CDP-G programming (Single-phase installation with 3 loads to connect).

VARIABLE

VALUE

Inverter power

10000 W

Number of inverters

1

Phase control

Single-phase

Injection margin

0 %

Load management Mode

Dynamic

Max. modulation value

90 %

Max. grid contribution

50 %

Reconnecting time

5 minutes

Relay 1

Relay 2

Relay 3

Power

2000 W

Power

2000 W

Power

1000 W

Min.
connection
time

2 minutes

Min.
connection
time

2 minutes

Min.
connection
time

90 minutes


Max. modulation value = 90%. This means that as long as the ratio be-

tween Pconsumed/Available PV Power is below 90%, the CDP-G will try to
connect the associated loads.

Max. grid contribution = 50%. This means that as long as the load can op-

erate with less than 50% of the power in the distribution lines, the CDP-G will
keep the loads connected. If it needs more than 50% of the grid power, it will
disconnect the loads connected to the relays.


In this situation, the CDP-G checks its working conditions to connect the first
load:

Condition 1:

𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃

𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 𝑃𝑃𝑖𝑃𝑖𝑖𝑃𝑖

𝑥 100 ≤ 𝑀𝑚𝑥. 𝑃𝑃𝑃𝑃𝑚𝑚𝑖𝑚𝑃𝑃 𝑖𝑚𝑚𝑃𝑃

(

4000

10000

𝑥 100 = 40%)  40% ≤ 90%  this condition is met

Condition 2:

-If Injection Margin = 0%

 It checks whether:

Pgrid < 2 x (0.03) x Pconsumed

-If Injection Margin

≠ 0%  It checks whether:

Pgrid < 2 x Injection Margin x Pconsumed

0 < 2 x 0.03 x 4000

 this condition is met

If the 2 conditions are met, the relay closes and connects

the load. (

Figure 27)