SECTION 5 • TESTING

GENERAL

In the event the relay is not to be installed immediately, store the relay in its original shipping carton.

When the relay is to be placed into service, it is recommended that the operational test procedure in this

section be performed prior to installation.

RELAY OPERATING PRECAUTIONS

Before installation or operation of the relay, note the following precautions:

1. A minimum of 0.2 ampere in the output circuit is required to ensure operation of current operated

targets.

2. The relay is a solid-state device. If a wiring insulation test is required, remove the connection

plugs and withdraw the cradle from its case.

3. When the connection plugs are removed the relay is disconnected from the operating circuit and

will not provide system protection. Always be sure that external operating (monitored) conditions

are stable before removing a relay for inspection, test, or service.

4. Be sure the relay case is hard wired to earth ground using the ground terminal on the rear of the

unit. It is recommended to use a separate ground lead to the ground bus for each relay.