Air purgingd

Soap water method

1. Remove the caps from the 2-way and 3-way valves.
2. Remove the service-port cap from the 3-way valve.
3. To open the 2-way valve turn the valve stem counterclock-

wise approximately 90°, wait for about 2~3 sec, and close it.

4. Apply a soap water or a liquid neutral detergent on the

indoor unit connection or outdoor unit connections by a soft
brush to check for leakage of the connecting points of the
piping.

5. If bubbles come out, the pipes have leakage

Evacuation

1. Connect the charge hose end described in the preceding

steps to the vacuum pump to evacuate the tubing and
indoor unit.
Confirm the "Lo" knob of the manifold valve is open.
Then, run the vacuum pump.
The operation time for evacuation varies with tubing
length and capacity of the pump. The following table
shows the time required for evacuation.

2. When the desired vacuum is reached, close the "Lo"

knob of the manifold valve and stop the vacuum pump.

Finishing the job

1. With a service valve wrench, turn the valve stem of liquid

side valve counter-clockwise to fully open the valve.

2. Turn the valve stem of gas side valve counter-clockwise

to fully open the valve.

3. Loosen the charge hose connected to the gas side ser-

vice port slightly to release the pressure, then remove
the hose.

4. Replace the flare nut and its bonnet on the gas side ser-

vice port and fasten the flare nut securely with an
adjustable wrench. This process is very important to pre-
vent leakage from the system.

5. Replace the valve caps at both gas and liquid side ser-

vice valves and fasten them tight.

This completes air purging with a vacuum pump.
The air conditioner is now ready to test run.

Gas side

Liquid side

Cap

Hexagonal wrench

2-way valve

(Open)

3-way valve

(Close)

Required time for evacuation when 30 gal/h vacuum

pump is used

10 min. or more

15 min. or more

If tubing length is less

than 10m (33 ft)

If tubing length is longer

than 10m (33 ft)

Indoor unit

Outdoor unit

Lo

Hi

Manifold valve

Vacuum pump

Pressure
gauge

Open

Close

Advertising
This manual is related to the following products: