PNEG-1708 GSI Modular Tower Dryer

7. Placing and Installing the Base/Unload Module

Base/Unload Module Placement Considerations

If the concrete foundation is ready and adequately cured, place the base/unload module on it and take
careful and complete consideration of the surrounding equipment. Be sure to consider any planned
options such as augers and any potential equipment to be added later.

1. Consider the location of the electrical box and control panel. Orient base/unload module so that

personnel will have adequate and safe access to the electrical box and control panel. Remember,
the Vision control box can be remote mounted.

(See Figure 7A.)

2. Consider any auxiliary equipment that will be used with the GSI Modular Dryer. One set of X-braces

on the unload may be removed without compromising structural integrity to allow for easier access.

3. Ensure that there is adequate overhead clearance for the entire tower dryer height and that the

clearance between the dryer walls and other equipment is sufficient to allow for catwalks
and/or platforms.

(See Figure 7B on Page 31.)

Figure 7A

Advertising