12. Gas Pipe Train Overview

Gas Pipe Train (Natural or LP) Overview Minimal Connections

Another beneficial feature of the GSI Modular Tower Dryer is the fact that the gas pipe train comes
pre-fitted and pre-assembled from the factory. This minimizes the connections that need to be made in the
field. The result, is a quicker and simpler installation process.

Only three (3) connections need to be made in the field to complete the gas train.

(See Figure 12B.)

Figure 12A

The three (3) connecting hoses for the gas train are for:

Liquid in

Vapor out

Return to burner

All three (3) are shown in the

Figure 12A

and ship in the crate along with catwalks, platforms and

other hardware.

Each hose has unique fittings and can only be installed in the proper location.