10. Lifting and Stacking the Modules

PNEG-1708 GSI Modular Tower Dryer

59

8. On all models of the GSI Modular Tower Dryer, the first two (2) connecting seams - between the

base/unload module and Module 2 and between Module 2 and Module 3 - require a nut and bolt in
EVERY hole of the connecting channel, both INSIDE and OUTSIDE of the dryer.

Figure 10K

a. For all other connecting seam after/above the first two (2), every other hole may be bolted.

OUTSIDE of dryer: Two (2) connecting channels between two (2) modules.

(See Figure 10K.)

NOTE: Every connecting hole must have a nut and bolt in place.

INSIDE of dryer: Two (2) connecting channels between two (2) modules.

(See Figure 10K.)

Outside channels - Bolted every other hole

Inside channels - Bolted every hole