12. Gas Pipe Train Overview

72

PNEG-1708 GSI Modular Tower Dryer

1. The largest connecting hose connects inside the dryer for the return to blower.

(See Figure 12C.)

Figure 12C

2. The remaining two (2) connecting hoses are installed inside the dryer as shown.

NOTE: All three (3) connecting hoses are pre-sized for correct connections and cannot be connected in

the wrong location as a result.

3/4"

1"