10. Lifting and Stacking the Modules
56
PNEG-1708 GSI Modular Tower Dryer
Lifting
1. Use four (4) clevis hooks to connect the crane’s lifting straps to the module.
2. Remember, all modules except the roof, lift from four (4) lift points around the outside of the unit.
NOTE: The recommended strap length for lifting is 6' long.
Figure 10E
Figure 10F