10. Lifting and Stacking the Modules

PNEG-1708 GSI Modular Tower Dryer

61

10. To stack additional sections, repeat the process as described above - always remember to line up

the ladder brackets on the modules -- and follow the suggested sequence illustrated earlier in
this chapter.

Consider the orientation of each module as it pertains to ladders and catwalks before placing it
on the module for connection.

Secure the module with clevis hooks and lifting straps. Lift with crane and place on top of
next module.

Place section together but do not fully rest upper section on lower section.

Use hammers and punches to line up connecting holes in channels both inside and outside
of dryer.

Insert nut and bolt and finger tighten in every hole or every other hole as appropriate.

Tighten with power impact.

Caulk gaps with clear food-grade silicone as needed.

Figure 10N Gap Un-Caulked

Figure 10O Gap Caulked

NOTE: ALWAYS stack and connect so that as much work as possible is done as close to the ground

as possible. Use the illustrations at the beginning of this chapter as a guide to accomplish this.

Caulk seam

Channels