10. Lifting and Stacking the Modules

PNEG-1708 GSI Modular Tower Dryer

61

10. To stack additional sections, repeat the process as described above - always remember to line up

the ladder brackets on the modules -- and follow the suggested sequence illustrated earlier in
this chapter.

•

Consider the orientation of each module as it pertains to ladders and catwalks before placing it
on the module for connection.

•

Secure the module with clevis hooks and lifting straps. Lift with crane and place on top of
next module.

•

Place section together but do not fully rest upper section on lower section.

•

Use hammers and punches to line up connecting holes in channels both inside and outside
of dryer.

•

Insert nut and bolt and finger tighten in every hole or every other hole as appropriate.

•

Tighten with power impact.

•

Caulk gaps with clear food-grade silicone as needed.

Figure 10N Gap Un-Caulked

Figure 10O Gap Caulked

NOTE: ALWAYS stack and connect so that as much work as possible is done as close to the ground

as possible. Use the illustrations at the beginning of this chapter as a guide to accomplish this.

Caulk seam

Channels