3 basics of the installation, 1 system planning, Basics of the installation -2 3.3.1 – YSI DIQ/S 182 XT-4 System 182 XT-4 User Manual

Page 16: System planning -2

Advertising
background image

Installation

System 182 XT-4

3 - 2

ba76026e01

01/2012

3.3

Basics of the installation

3.3.1

System planning

Overview of planning

steps

Fig. 3-1

System planning

- Position power supply modules near

main consumers (e. g. UV/VIS sensors)

Power requirement=

SP of all consumers

(take into account the relative
switching on time of valves)

- Number and types of required sensors
- Measuring locations to be designed
- Distances
- Infrastructure, process environment etc.

Rough planning

Determination of power requirement

Rating

Fine adjustment

IQ

topology + layout

S

ENSOR

N

ET

Power requirement of components

Determination of rating

of power supply modules

Fundamentals of planning

Start

End

Arrangement of

power supply modules

- Sum of all line lengths max. 250 m