5.2.5

Calibration points

Calibration can be performed using one to five buffer solutions in any order
(single-point to five-point calibration). The meter determines the following
values and calculates the calibration line as follows:

26. Set the nominal buffer value for the measured temperature with

<><>

.

27. Accept the set calibration value with <ENTER>.

The calibration display for the next buffer appears (voltage display).

28. Use <M> to finish calibration or

Continue calibrating using the next buffer with <ENTER>.

After the fifth buffer has been measured the calibration is automat-
ically finished. Then the calibration record is displayed.
The calibration line is determined by linear regression.

Determined

values

Displayed calibration data

1-point

Asy

Zero point = Asy

Slope = Nernst slope

(-59.2 mV/pH at 25 °C)

2-point

Asy
Slp.

Zero point = Asy

Slope = Slp.

3-point to
5-point

Asy
Slp.

Zero point = Asy

Slope = Slp.

The calibration line is calculated by lin-
ear regression.

You can display the slope in the units, mV/pH or % (see section
7.1.1 C

HANGING

THE

SETTINGS

FOR

P

H

MEASUREMENTS

, page 38).