Commissioning

Multi 1970i

12

Connecting the plug-in

power supply unit

3.3

Initial commissioning

Perform the following activities:

z For mains operation and charging the battery: Connect the plug-in

power supply (see section 3.2 P

OWER

SUPPLY

).

z Set the date and time.

Setting the date and

time

1

Connect the plug (1) to the socket (2) of the measuring instru-
ment.

2

Connect the original WTW plug-in power supply (3) to an easily
accessible mains socket.

2

1

3

1

Press the <M> key and hold it down.

2

Press the <ON/OFF> key.
The display test appears briefly on the display.

3

Press the <RUN/ENTER> key repeatedly until the date flashes
on the display (Day.Month display indicator).