4.4. MOVING THE ASSEMBLED SECTIONS

1. With the crane, lift and lower the first

fully-assembled Weighbridge Section

into the end of the Pit.
─ Set down the section slowly onto the

wooden cribbing blocks.


2. Using the crane, lift and lower the

second fully assembled Section into the

Pit. Use hydraulic jacks also to lift the

assembly slightly and shift into proper

alignment.


3. Fasten these two main girder sections

together with the cross beams and

hardware, using the 3/4" drift pins to

assist in aligning the plate and girder

holes.
─ Secure each joint tightly


4. Continue placing, blocking, and

fastening the main girder sections until

all pieces are in position.

5. Once all the sections are installed,

ensure that the measurements and

elevations are correct according to the

Certified Drawing Specifications

.