Concrete deck forming and pouring, American concrete institute code – Fairbanks Tundra Series Truck Scale User Manual

Page 32

Advertising
background image

Section 4: Scale Installation

12/12

32

51193 Revision 5

4.7. CONCRETE DECK FORMING AND POURING

The deck consists of poured

reinforced concrete over corrugated

sheet steel laid length-wise on the

weighbridge. A channel coping

surrounds the deck.







1. Pour the concrete flush with the top of the

channel coping.

2. Pour concrete. The concrete should have

a minimum compressive strength of
4,000 psi.

─ Take several test cylinder samples

during this process.

3. Place the concrete into position by direct

chute method.
─ Ensure thorough consolidation by

using a spud type vibrator as required.

All concrete work

MUST conform to

standards set forth by the

American

Concrete Institute Code.

4. Before the concrete has fully set, "broom"

finish it with textured grooves

perpendicular to the long axis of the scale.

Advertising