To ensure proper operation of each unit, qualified person-

nel should perform the start-up and complete the checklist

below and the start-up report in

Appendix H

for permanent

record. A completed checklist will provide valuable informa-

tion for personnel performing future maintenance.

All units are factory run tested. Blowers, heat wheel and

compressors (if equipped) are set up to run correct when

power is connected. If any one blower is running back-

wards or compressor is making loud noises disconnect

power and switch two leads (on three-phase power) to en-

sure proper rotation and avoid damage.
If units are equipped with compressors power must be

turned on for 24 hours prior to a call for cooling, for the

compressor crank case heaters to be energizing to prevent

possible damage.

The BacStat II interface module (if equipped with DDC con-

trol package and mounted remotely) may be temporarily

connected at the unit for checkout. Ensure it is connected

to the Net 2 contacts otherwise it will not give readings.

1. Before proceeding complete the pre start-up check-

list.

2. Check that all access panels or doors are closed.

3. Turn the main disconnect to the ‘On’ position.

4. Set the timer, selector switch or BMS contact to the

ventilation control scheduling mode selected and

check operation according to sequence. Only one of

the following modes selected can have their contacts

closed or jumped.

a. Occupied ventilation (Ov): With the occupancy

contact closed or a jumper placed across termi-

nals, heat wheel starts (not in free cooling), de-

frost recirculation damper closes (if equipped),

outside and exhaust air dampers open fully,

the supply blower starts and after exhaust air

damper opens fully, the exhaust blower starts.

b. Unoccupied recirculation (Ur): With the unoc-

cupied recirculation contact closed or a jumper

Start-up Procedure

IMPORTANT

A completed copy must be sent back to the factory for

warranty validation and for factory assistance.

Before requesting start-up, check that the installation is

complete and unit is ready. Complete the pre start-up

check list below and in the

Appendix H

for each unit as

items are checked.

1. Set the electrical disconnect to the ‘Off’ position.

2. Check the unit for obstructive packaging, objects near

or in blowers, dampers, heat wheel, etc. Remove all

red tie down bolts on fan assemblies and heat wheel if

so equipped.

3. Check that the fans and heat wheel are rotating

freely.

4. Check blower wheels and drive set screws. Tighten if

required.

5. Check belt alignment and tension.

6. Check that the air filters are installed and clean. Re-

place if necessary.

7. Check coils (if equipped) if fins have been damaged

in transit or construction and are clean. Straighten fins

with fin comb and clean coil if required.

8. Check the refrigerant components and piping that they

are in good condition and have no damage or leaks

from shipping or installation.

9. Check that the water strainer has been installed for a

WSHP with a brazed heat exchanger.

10. Check that ductwork is connected and complete.

11. Check that condensate drain connections have been

trapped, installed correctly and filled.

12. Check that all shipped loose or field supplied compo-

nents have been correctly installed and wired and that

start interlocks have been completed for the ventilation

control desired.

13. Check that the standard field wiring (FW) terminal

diagram has been marked up accordingly and left with

the unit.

14. Check that all power supplies and control wiring have

been inspected and approved by the Local Authorities

having jurisdiction.

15. Check all factory and field wiring connections for tight-

ness. Tighten if necessary.

16. Check that all fuses are properly installed in holders.

17. Check the voltage at the disconnect switch against the

nameplate and against phase-to-phase readings on

three-phase. If the voltage is not within 10% of rated

or 2% of phase-to-phase, have the condition corrected

before continuing start-up.

18. Check that all field piping and venting installation and

connections for the heating and cooling options have

been completed and test.

19. Set the heating and cooling enable switches to the

‘Off’ position.

Start-up

Pre Start-up Procedure