2 short set-up (factory setting), 1 switch-on sequence, Commissioning – Lenze 8200 series User Manual
Page 34
Advertising
Commissioning
5-2
UOMu_^MVMO
5.2 Short set-up (Factory setting)
5.2.1
Switch-on sequence
Step
1.Switch on mains voltage
2.Select the direction of rotation.
D
CW rotation:
- Apply a LOW signal to terminal E4 (0...+3V).
D
CCW rotation:
- Apply a HIGH signal to terminal E4 (+12...+30V).
3.Select the setpoint.
Apply a voltage 0...+10 V to terminal 8.
4.Enable the controller.
Apply a HIGH signal (+12...+30V) to terminal 28.
5.The drive is now operating according to factory
setting.