5.2 Short set-up (Factory setting)

5.2.1

Switch-on sequence

Step
1.Switch on mains voltage
2.Select the direction of rotation.

D

CW rotation:
- Apply a LOW signal to terminal E4 (0...+3V).

D

CCW rotation:
- Apply a HIGH signal to terminal E4 (+12...+30V).

3.Select the setpoint.

Apply a voltage 0...+10 V to terminal 8.

4.Enable the controller.

Apply a HIGH signal (+12...+30V) to terminal 28.

5.The drive is now operating according to factory

setting.