General Meter Setup

This section describes how to configure the PM174 for your

particular environment and application using PAS.

Basic Meter Setup

Before operating your meter, provide the device with basic

information about your electrical network.

To enter the Setup dialog, select the device site from the list
box on the PAS toolbar, and then select General Setup from
the Meter Setup menu.

The following table lists available device configuration options.

Parameter Options Default

Description

Basic Configuration
Wiring mode

See Table below

4LN3

The wiring connection of the device

PT ratio

1

1.0-6500.0

1.0

The phase potential transformer’s
primary to secondary ratio

PT Ratio multiplier

Ч1, Ч10

Ч1

PT Ratio multiplication factor. Used in

extra high voltage networks to
accommodate the PT ratio for 500 kV
and higher networks.

CT primary current 1-20000 A

5 A

The primary rating of the phase
current transformer

Nominal voltage

10-690 V

120 V

The nominal secondary line-to-neutral

(in configurations with a neutral wire)
or line-to-line voltage (in 3OP2, 3OP3
and 3DIR). Used as a reference
voltage for the IEEE 1159 Power
Quality recorder.

Maximum demand
load current

0-20000 A

0

The maximum demand load current
(0 = CT primary)