INSTALLATION

2-5

The location of the 1-1/4" inlet gas connection is

on the right side of the unit as shown in Figure

2.7.

All pipe should be de-burred and internally

cleared of any scale or iron chips before

installation. No flexible connectors or non-

approved gas fittings should be installed. Piping

should be supported from floor or walls only and

must not be secured to the unit.

A suitable piping compound, approved for use

with gas, should be used sparingly. Any excess

must be wiped off to prevent clogging of

components.

To avoid damage to the unit, when pressure

testing gas piping, isolate the unit from the

supply gas piping. At no time should there be

more than 14” W.C. the unit. Bubble test all

external piping thoroughly for leaks using a

soap and water solution or suitable equivalent.

The gas piping must meet all applicable codes.

2.4.1 GAS SUPPLY PRESSURE

REGULATOR

An external, in-line, supply gas regulator

(supplied by others) should be positioned as

shown in Figure 2.7. Union connections should

be placed in the proper locations to allow

maintenance of the regulator if required

NOTE:

An individual gas pressure regulator must

be installed upstream of each KC1000. The

regulator must regulate gas pressure to 8.5”

W.C. at 1,000,000 BTU/H for natural gas

and propane units

.

The maximum static inlet pressure to the unit

must be no more than 14” water column.

Minimum gas pressure is 8.5” W.C. for FM gas

trains and 8.9” W.C. for IRI gas trains when the

unit is firing at maximum input. Gas pressure

should not exceed 10.5” W.C. at any time when

firing. Proper sizing of the gas supply regulator

in delivering the correct gas flow and outlet

pressure is mandatory. The gas supply pressure

regulator must maintain the gas pressure at a

regulated 8.5” W.C. minimum for FM gas trains

and 8.9” W.C. for IRI gas trains at maximum

BTU input (1,000,000 BTU/HR) for natural gas

and propane installations. The supply gas

regulator must be of sufficient capacity volume,

(1000 cfh), for the unit and should have no more

than 1" droop from minimum to full fire. The

supply gas regulator must also be rated to

handle the maximum incoming gas pressure to

it. When the gas supply pressure will not exceed

14” W.C. a non-lock up or flow through style

regulator may be used. When supply gas

pressure will exceed 14” W.C., a lock up style

regulator must be used. The gas supply

regulator must be propery vented to outdoors.

Consult the local gas utility for exact

requirements concerning venting of supply gas

regulators.

CAUTION!

A lockup style regulator must be used when

gas supply pressure exceeds 14” W.C.

2.4.2 MANUAL GAS SHUTOFF VALVE

A 1-1/4” manual gas shut-off valve is furnished

with each unit. The valve should be positioned

as shown in Figure 2.7. The manual gas shut-of

valve must be installed upstream of the supply

regulator in a readily accessible location.

Figure 2.7

Gas Supply Regulator and Manual Shut -Off

Valve Location

2.4.3 IRI GAS TRAIN KIT

The IRI gas train is an optional gas train

required in some areas by code or for insurance

purposes. The IRI gas train is factory pre-piped

and wired. (Refer to Appendix F, Drawing No.

SD-A-584).

2.5 ELECTRICAL SUPPLY

The AERCO Gas Fired Equipment Electrical

Power Wiring Guide, (GF-1060), must be

consulted in addition to the following material

before wiring to the unit is started. AC power

connection to the unit are made at the Power

Box.This box is located on the front right side of

the unit as shown in Figure 2.8. Conduit should