35

4.5.2 Mechanical Coupling for the "Chemically Active" Option

If you are using a Sunny Central with the "Protection against chemically active substances" option,
the switch cabinets must be connected to one another as described below.

Mounting the Switch Cabinet Units

1. Attach the included sealing material all around the cabinet frame (A) of the AC cabinet.

2. Position the switch cabinet units near the installation location.
3. During mounting, insert the PE cable through the

cable gland (A).

4. Set up the switch cabinet units in the installation

location.

5. Connect the PE cable, see 5.2 ”Connecting the

Internal PE Connection” (page 42).
☑ The switch cabinet units are mounted and can

now be screwed together.

A

A

Advertising