75

2. Drill a hole in the copper bar as illustrated in the

figure to the right.

3. Use a ring terminal lug (25 mm² M8) to connect the internal power supply transformer to the

copper bar.

NOTICE!
Operational reduction of the Sunny Central due to faulty connection!

Configuration of the components for connection
(from back to front):

1. Bolt, M8x25
2. Washer
3. Locking washer
4. Copper bar
5. Ring terminal lug
6. Washer
7. Locking washer
8. Nut

100 mm

40 mm

o 8,5 mm