Power-Up Diagnostics

An LED test is performed each time the drive is powered up. The initial boot sequence may

take several seconds. After the LEDs have completed the diagnostic LED sequence, the option

is successfully initialized. The LEDs then assume operational conditions as shown in

Table 3

.

Table 4 Power-Up Diagnostic LED Sequence

Sequence

Module Status (MS)

Network Status (NS)

Time (ms)

1

Green

OFF

250

2

Red

OFF

250

3

Green

OFF

4

Green

Green

250

5

Green

Red

250

6

Green

OFF

4 Option Components