Installation Checklist

- All packing materials and restraints have been removed from each cabinet.

- Each cabinet in the UPS system is placed in its final installation location.

- A ground bond is installed between any cabinets that are bolted together.

- All switchboards, conduits, and cables are properly routed to the UPS and auxiliary cabinets.

- All power cables are properly sized and terminated.

- A ground conductor is properly installed.

- If a bypass input neutral connection is used, no other N‐G bonds exist downstream from the UPS.

- Battery cables and harnesses are terminated on E4 and E5.

- Internal battery cabinet connections have been completed (bus bars, plugs, etc.).

- Shunt trip signal wiring is connected from UPS to battery breaker(s).

- Air conditioning equipment is installed and operating correctly.

- The area around the UPS system is clean and dust‐free. (It is recommended that the UPS be installed on a level,

sealed concrete pad or floor.)

- Adequate workspace exists around the UPS and other cabinets.

- Adequate lighting is provided around all UPS equipment.

- A 120V service outlet is located within 7.6m (25 ft) of the UPS equipment.

- Each Remote Monitor Panel (RMP) is mounted in its installed location. (OPTIONAL)

- The control wiring for each RMP is terminated inside the UPS cabinet. (OPTIONAL)

- The remote emergency power-off (REPO) device is mounted in its installed location and its wiring terminated inside

the UPS cabinet. (OPTIONAL)

- Summary alarms and/or building alarms are wired appropriately. (OPTIONAL)

- A Relay Interface Module (RIM) is mounted in its installed location and its wiring is terminated inside the UPS cabinet.

(OPTIONAL)

- A remote battery disconnect control is mounted in its installed location and its wiring is terminated inside the UPS and

battery cabinets. (OPTIONAL)

- Circuit breakers with adjustable trip mechanisms adjusted to match site requirements.

- Debris shields covering ventilation grills are removed from all cabinets.

- Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.