Martin Christ Epsilon 2-10D LSCplus User Manual

Page 79

Advertising
background image

Freeze-dryer EPSILON 2-10D LSCplus

6 Operation

Version 04/2013, Rev. 1.5 of 16/12/2014 • sb

79

Translation of the original operating manual

Option: Aeration, stoppering, storage
(see chapter 6.6 - "Optional extensions and special equipment")


1 Button for selecting

the variant

2 Set value "Aeration"
3 Set value "Aeration

after stoppering"

4 Set value

"Stoppering"

5 Set value "Storage"

Fig. 70: Dialog box "Aeration, stoppering, storage"


Repeated pressing of this button enables the user to choose between the
following variants:
• Deactivated
• Aeration (up to the "Aeration" value) and subsequent storage
• Stoppering (at drying vacuum followed by aeration up to atmospheric

pressure) with subsequent storage

• Aeration (up to the "Aeration" value), stoppering (followed by aeration

up to atmospheric pressure) with subsequent storage

The set values of the parameters can be adapted by way of the respective
button if the button is shown with a blue background.

"Aeration, (stoppering), storage" procedure:
1. Aeration up to the desired partial vacuum ("Aeration" value):

After the actual freeze-drying process has been completed, the ice
condenser continues to be cooled and the shelves are held at the
temperature of the last drying section. The system is aerated until the
desired partial vacuum is reached ("Aeration" value, see the illustration
above, item 2).

NOTE

The product vials must be sealed at a chamber pressure below 900 mbar
in order to prevent the stoppers from being pushed out of the vials at low
atmospheric pressure.


2. Stoppering followed by aeration up to atmospheric pressure

While the ice condenser continues to be cooled and the shelf
temperature is maintained, the shelves are moved together in order
press the Lyo stoppers into the product vials. The stoppering pressure
is maintained over the specific "Stoppering" time (see the illustration
above, item 4). The subsequent final aeration is performed in two steps.
In the first step, the system is aerated up to the partial vacuum that is

Advertising