Run a Trial Piece

Once material is in place, press

Trial Piece so you can check that

setup is correct.
You can make minor changes to the job settings at this stage if the

trial piece needs fine tuning. Enter setup as described on page

2-9, then use the

Prev (◄), Next (►) and Change (+/-) buttons as

required to modify job settings. When you’ve made the necessary

changes, press

Setup again to return to run mode. The inserter

saves the job with the new settings.
Notes:
1. When using linked feeding,* load both sheet feeders before run-

ning a trial piece.

2. If you load material during a run which seems to have different

characteristics (weight, color shade, etc.), or if you have any

problems with double detection, run another trial piece. This

forces the machine to recalibrate the double detect function for

the new material in case the batches vary slightly.

Start Machine Operation

Press

Start to begin automatic operation.

The machine runs until either material runs out or you press the

Stop button.
Note: If the machine is set for linked feeding, the display shows:

1 > 2 > 1

This confirms that feeding will automatically switch between

sheet feeders. See page 2-13 for more details.

* “Linking” is a method of using two feeders such that when one feeder

runs out of material, the next “linked” feeder automatically starts feeding.

Linking feeders allows you to process a higher volume of material before

reloading. Linked feeders are sometimes referred to as “cascading”