Create readiness to operate

When you switch on the operating and load voltages, you
must observe the waiting times specified.

Wait

ţ 10 s

Set ENABLE

Initialization and
self test

Switch on the operating
voltage and load voltage at
the same time

Set ENABLE

Switch on the load voltage

Wait

ţ 1 s

Start: Create readiness to
operate

Wait

ţ 10 s

Reset ENABLE

Switch on the operating
voltage

1

Switch on

power supply

at same

time?

Yes

No

1

2

2

2

1

Operating and load voltage supplies of the SPC200

2

The voltage must in each case be stable at 24 V DC −5 %/+25 %

Fig. A/1:

Create readiness to operate