SECTION 6 - TROUBLESHOOTING

3121228

– JLG Lift –

6-31

Code 33 - RESERVED

Code 34 - P2-Auxiliary #1 - Inhibit

Check For These Obvious Conditions First:

• Platform Gates Closed.
• Pressure on the Platform Footswitch (after power up).

NOTE: In the procedures below, if you check continuity between pin 6 and 16 it should show open circuit, when the platform

gates are closed and nothing is on the foot switch. When you step on the foot switch with the gates closed, you should
see a closed circuit.

Code 35 - P2-Auxiliary #1 - Tie Down

Check For These Obvious Conditions First:

• Pressure on the Platform Footswitch during machine power up.

NOTE: In the procedures below, if you check continuity between pin 6 and 16 it should show open circuit, when the platform

gates are closed and nothing is on the foot switch. When you step on the foot switch with the gates closed, you should
see a closed circuit.

Code 36 - RESERVED

Code 37 - RESERVED

Table 6-32. Code 34 - P2-Auxiliary #1 - Inhibit

STEP

ACTION

SPEC

YES

NO

1.

At the Ground Control Module, P2 connector, check the voltage across
pins-16 (orange/red 49-5) and 6 (black 12) is reading within specification?

0 - 2V DC

Go to Step 2

Replace Ground

Control Module

2.

Remove the P2 connector from the Ground Station Module; check continu-
ity of the individual wires in the platform harness. (P2 to platform junction
box)
,

Go to Step 3

Repair or

Replace Platform

Harness

3.

Check continuity of gate switches and foot switch circuit. (Switches are
wired in series; doors shut and foot switch depressed, circuit will be
closed)

Consult Factory

Replace Compo-

nent or Repair

Wires

Table 6-33. Code 35 - P2-Auxiliary #1 - Tie Down

STEP

ACTION

SPEC

YES

NO

1.

At the Ground Control Module, P2 connector, check the voltage across
pins-16 (orange/red 49-5) and 6 (black 12) is reading within specification?

0 - 2V DC

Go to Step 2

Replace Ground

Control Module

2.

Remove the P2 connector from the Ground Station Module; check continu-
ity of the individual wires in the platform harness. (P2 to platform junction
box)
,

Go to Step 3

Repair or

Replace Platform

Harness

3.

Check continuity of gate switches and foot switch circuit. (Switches are
wired in series; doors shut and foot switch depressed, circuit will be
closed)

Consult Factory

Replace Compo-

nent or Repair

Wires

Advertising