These work cells are used to assemble and pack the finished BizBikes. The setup and
process (per item) durations are part dependent. Each assembly operation requires two
labor units from the labor pool for its entire duration.

S

UBASSEMBLY

These work cells are used to assemble component parts (manufactured and purchased)
into subassemblies that are placed in stock for future required orders. The setup and
process (per item) durations are part dependent. Each subassembly operation requires one
labor unit from the labor pool for its entire duration.

F

INISH

AND

C

UT

These work cells are utilized for operations necessary to produce the component parts
required for the subassemblies. The setup and process (per item) durations are part
dependent. These work cells are manned by a dedicated operation and do not require labor
from the labor pool.

M

ACHINE

AND

B

END

These work cells are utilized for operations necessary to produce the component parts
required for the subassemblies. The process (per item) durations are part dependent. These
work cells are manned by a dedicated operation and do not require labor from the labor
pool. The setup durations for these work cells are sequence dependent and defined in
matrix MM for the Machine work cell and matrix BM for the Bend work cell. These two
matrices are shown below.

Machine Setup Matrix: MM

SSD Frame

SHP Frame

Handlebar

Neck Post

SSD Frame

0.00 0.12 0.53 0.58

SHP Frame

0.14 0.00 0.55 0.62

Handlebar

0.64 0.66 0.00 0.26

Neck Post

0.57 0.61 0.33 0.00