Prepare hoses for sensors, Install blockage sensors, Prepare hoses for sensors install blockage sensors – Great Plains 3N4010HDA Predelivery Manual User Manual

Page 34

Advertising
background image

32

3N-4010HDA and ADC2350B

Great Plains Manufacturing, Inc.

196-444Q

10/10/2008

Prepare Hoses for Sensors

Refer to Figure 37

DICKEY-john Recon-II blockage sensors

require a

hole in the hose for the detectors

. The sensor has flex-

ible flaps which are tie-wrapped around the seed hose.
The long flap

goes over the short flap

.

Note: Use a hole saw to make the hole. Use a high speed

drill (to minimize rough edges), and cut slowly (to
minimize risk of drill-through).

Using a drill bit is likely to damage the hose.

Refer to Figure 38 (showing hole on top)

100. Drill one hole in each secondary seed hose at each

tower. Check the first hole for sensor fit before drill-
ing the remaining holes.

The hole location is approximately:

13in (33cm)

from where the hose enters the tower.

The hole diameter is:

11

16

to

3

4

in (17-19mm)

Make the hole on the underside of the hose (toward
center of tower), or rotate the hose to hole-under
after drilling or installing sensor.

Install Blockage Sensors

Refer to Figure 39

101. Select one:

467420352S1 RECON II

102. Orient sensor

with signal lead toward opener.

Insert the detector head

in the hose hole.

Wrap the short flap

around the hose.

Wrap the long flap

over the short flap.

Check that the long flap overlaps by at least

1

4

in

(6mm), but by no more than 1in (25mm). If the flap
is too long, cut off any excess. Re-check overlap.

103. Select two ties from either:

110110050 TY WRAP BUNDLE 50-14"
110110099 TY WRAP BUNDLE 100-14"

Secure the sensor to the hose with ties.

Figure 37

Blockage Sensor

28197

93

1

2

3

93

1

2

3

Figure 38

Sensor Hole Location

28194

4

5

4

5

Figure 39

Mount Sensor

28195

2

93

89 90

Opener

Tower

93

93

1

3

2

89

90

Advertising