Powering Up the Drive

Review the following checklist before applying power.

Item to Check

Description

Power supply

6-Phase/12-Pulse Isolated 380 to 480 Vac 50/60 Hz, 30 electrical degrees phase-shifted each phase
Properly wire the power supply input terminals (R/L1, S/L2, T/L3, R1/L11, S1/L21, T1/L31).

<1>

Check for proper grounding of drive and motor.

Drive output terminals and

motor terminals

Properly wire drive output terminals U/T1, V/T2, and W/T3 with motor terminals U, V, and W.

Control circuit terminals

Check control circuit terminal connections.

Drive control terminal status

Open all control circuit terminals (off).

Status of the load and connected

machinery

Decouple the motor from the load.

<1> Install a 6-Phase/12-Pulse isolation transformer with each of the output windings phase-shifted by 30 electrical degrees or use a Hybrid 6-Phase

topology.