Operation – Casella CEL CEL-450 User Manual

Page 46

Advertising
background image

Operation Press

Display Shows

Comments

5. When the

Measure-

ment

screen

looks like

this

The last setup used was

narrow band.

When narrow band

measurement with B and C

models is required, follow

the instructions given in

Section 5.1.3.

When broadband

measurement is required,

change the bandwidth to

broadband as described in

Section 3.1, then proceed

from Section 5.1.2.

5.1.2 Broadband Measurement

Operation Press

Display Shows

Comments

1. Start from

the

Broadband

Measure-

ment

screen

Continue broadband

measurement.

2. Start a

measure-

ment run

(i.e. store

data)

shows a run is now in

progress.

When periods are disabled,

the time since the start of

the current run is shown at

the top right.

When periods are enabled,

the number of completed

periods is shown at the top

left of the screen and the

time since the start of the

current period at the top

right.

3. If a screen

like this is

displayed

while a

CEL-490 is

being used

The delay timer has been

enabled. The clock icon

shows that this is a Wait

screen with current date and

time, plus the time at which

the run will start.

Once the run has started, go

to Step 5.