SECTION 2
CALIBRATION
2.1 CALIBRATION
SETUP
Prior to starting the calibration procedure, gather the necessary equipment
(Section 2.1.1), then power up the chassis and allow it to warm up for 15
minutes.
2.1.1
E
QUIPMENT
R
EQUIRED
•
DC Voltage Standard: Krohn-Hite EDC 521
•
Current Shunt: Prodigit 7550
•
Digital Multi-Meter (DMM): Agilent 34401A
•
DC Power Supply: Sorensen SG Series (Supply depends upon
models being calibrated.)
2.2
DVM CALIBRATION
Connect the SL Series electronic load as shown in Figure 2-1
Figure 2-1. Connections for DVM Calibration Items 1-4)
Press MODE and LEVEL keys simultaneously to enter Calibration Mode and
to be at Item 1 to start calibration.
SLM/SLH Calibration Manual