7. 4.00" Corrugation Farm Commercial Hopper Tanks (FCHT) 4-6 Rings

66

PNEG-1451 Ladder, Safety Cage and Platform for Hopper Tanks

FCHT Ladder, Safety Cage and Platform Instructions 4-6 Rings

All grain bin packages, from 4 ring to 6 ring and 18' to 24' diameter, contain the correct components for
assembly. Read and follow the complete instructions for correct placement of parts. Be sure and use the
charts to determine the appropriate number and size parts to be used based upon the number of rings in
the bin. Failure to do so may result in an improper fit or shortage of parts. Pay particular attention to the
location of ladders and platforms as they relate to the equipment and other structures in the area.

Eave Starter Bracket Installation

Correct placement of the eave ladder starter bracket is critical to assure proper fit of all ladder components
and to assure the correlation is correct between the platforms for proper installation of the access door
platform. If the eave starter brackets are mislocated, standard installation of the access door platform will
not be possible.