Eave platform mounting angle installation – Grain Systems Bin Accessories PNEG-1451 User Manual

Page 71

Advertising
background image

7. 4.00" Corrugation Farm Commercial Hopper Tanks (FCHT) 4-6 Rings

PNEG-1451 Ladder, Safety Cage and Platform for Hopper Tanks

71

Eave Platform Mounting Angle Installation

Figure 7H

shows the location of the platform mounting angles. Each angle must be mounted starting

8" above the top horizontal seam of the second ring with the first mounting angle offset 9-3/8" from the
right hand starter bracket. The second mounting angle must be located 56-1/4" from the first mounting
angle. The dimensions and locations of these angles are critical for proper fit of all parts. Using the platform
mounting angels as guides, field drill 3/8" holes in the sidewall every 8".

(See Figure 7H.)

Figure 7H

Advertising