24' Leveling Band Post Installation

Install the leveling band posts on the floor as shown

in Figure 8G

.

The fourth and eighth holes in the floor sheet indicate the location of the leveling band posts. Attach posts
with 5/16" x 1-1/4" bin bolts (S-277). The third hole from the bottom of the sheet, there will be
eight (8) posts (one every third sheet). In the eighth hole there will be four (4) posts (one every sixth sheet).
After all of the posts have been installed fill the unused holes with 5/16" x 1-1/4" bin bolts.