8. Installation

46

PNEG-1510 Top Dry 24', 30' and 36' Manual Batch

Flashing Bolt Installation

Install the eave flashing bolts (5/16" x 1-1/4") through the sidewall and tighten first nut. Note at the vertical
sidewall seams, one bolt is turned around to avoid interference with eave flashing.

(See Figure 8J.)

Figure 8J

Eave Flashing Installation

Install the eave flashing centered on the floor sheet (one per) with the bent edge towards the sidewall
install a fender washer (S-3671) and nut. Screw the flashing to the flashing angle at the dump hopper
opening with five (5) #10 self-drilling (S-280) screws and screw the flashing pieces together where they
overlap with three (3) #10 self-drilling (S-280) screws.

(See Figure 8K below

and Figure 8L on Page 47.)

Figure 8K

Left bolt on the each vertical sidewall seam
level with the eave flashing bolts (as viewed
from inside the bin) is to be installed bolt in,
nut out, as shown in

Figure 8J

.

Flashing Attachment
1) Sidewall
2) Flashing (TD-100648)
3) Floor sheet
4) 5/16" x 1-1/4" Bin bolt

Note that there is a nut in
between the sidewall sheet
and the flashing sheet.