4.4.4

Actions of Calibration

Calibration 1 to 3 is allowed to be specified only when the measurement status is in Stream
Sequence 1 to 4 or in Stream (continuous) 1 to 4. Actions are different according to the
specified calibration (validation) method.

• Automatic Calibration

The same action is performed when the starting time comes at any timing during analysis.

(1)

An action when the starting time of Automatic Calibration 1 comes while the measure-
ment status is in Stream Sequence 1 and the operation mode is in Run, is shown in
Figure 4.13.

W7

W8

W3

W1

W2

S1

S2

S7

W7

S7

S8

S3

Starting time of Automatic Calibration 1

Time

Stream Sequence 1

Stream Sequence 1

Calibration 1

S1 to S8: Analysis cycles for streams 1 to 8

W1 to W8: Warming up time for streams 1 to 8

F0413.EPS

Figure 4.13

Action of Automatic Calibration (1)

(2)

An action when the starting time of Automatic Calibration 1 comes while the measure-
ment status is in Stream (continuous) 1 and the operation mode is in Run, is shown in
Figure 4.14.

W7

W8

W1

W1

W1

S1

S1

S7

W7

S7

S8

S1

Starting time of Automatic Calibration 1

Time

Stream (Cont) 1

Stream (Cont) 1

Calibration 1

S1 to S8: Analysis cycles for streams 1 to 8

W1 to W8: Warming up time for streams 1 to 8

F0414.EPS

Figure 4.14

Action of Automatic Calibration (2)