2. Operation Data

Operation data is supplied with the operation manuals in the delivered package and con-
tains the following required to use the gas chromatographs.

Process conditions and measurement range

Instrument specifications and operating conditions

Standard sample for calibration

Column system and column

Miscellaneous data
Chromatogram, base line, repeatability, power supply voltage variation, etc.

Analyzer flow diagram and installation

Parts composition table

General connection diagram

Sampling system diagram (only if supplied by Yokogawa)

Is the System Ready?

Before reading this manual, the following preparations must have been completed.

The system must be unpacked and installed in the correct place.

The piping for the utility gases such as carrier and calibration gases must be com-
pleted, followed by leak checking.

The wiring for the power supply and others must be completed.

If these have not been completed yet, see the Installation Manual (TI 11B03A03-13E).
After completion, return to this manual and do the following:

If the system power is on, turn off the power.

Shut off all the gases at the flow control units.

Please read the following respective cautions (General Precautions, Caution of
using Explosion-Protection Instruments, on Piping Construction, and on Piping
Work) before installing and using the GC1000 system.