Installation of a System 25 requires the completion of a number of basic

steps, similar to those required to install any customer switching system.
Assuming that the building (station) wiring is already in place, the
recommended sequence of steps for installation of the system is as follows:

1.

Preinstallation Requirements

2. Install System Cabinets

3. Power Up and Initialize System

4.

Install Cross-Connect Equipment (See Note below.)

5. Install Modular Bulk Power Supply (Optional)

6. Connect Cabinets to

7. Connect Cabinets to

8. Install

9. Install

10.

Install

Trunk Access Equipment

Station Interconnect Panel (SIP)

Customer’s Peripheral Equipment

Terminals

Auxiliary Equipment

11.

Test System

Note:

Step

4

can be done before Steps 2 and 3 if the cross-

connect equipment is delivered before the cabinets.